news
News Center
Providing high-quality power to the world
Search productSearch post
news
Providing high-quality power to the world
Substation earthing continuity acceptance should confirm that installed bonds and conductive paths match the approved design before energization. A drawing may show the intended connection, but the site team still needs evidence of accessible terminals, secure connections, test points and resolved exceptions.

Agree which equipment, enclosures, cable trays, doors, frames and interfaces belong to the inspection package. Use approved earthing drawings and the project test procedure to identify each bond and its destination. Record temporary construction connections separately from permanent connections so they are not mistaken for completed work.
Inspect accessible contact surfaces, conductor routing, mechanical protection, corrosion protection, identification and fastener condition. Confirm that flexible bonds allow the intended movement of doors or removable panels without strain. Where a connection is hidden after installation, obtain the inspection record and photographs taken before closure.
A torque mark can show that a joint was checked, but it does not replace the approved fastening procedure or the required test. If a joint is opened for correction, update its inspection and test record after reassembly.
The test team should follow the project-approved method, instrument range and acceptance criteria. Record the instrument identity and calibration status, the exact points measured, the result and the date. A single “pass” against a whole substation is too broad for later fault tracing. Where the equipment cannot be safely accessed at the planned test stage, document the reason and the approved alternative evidence.
Typical exceptions include missing bond tags, paint under a contact surface, an unverified tray joint, an inaccessible test point or a bond routed across a maintenance opening. Assign each item an owner, corrective action and retest requirement. Do not erase the original result; retain both the failed observation and the accepted closure evidence.
For an EPC handover, the value of this package is traceability: a future maintenance team can identify what was tested, where it was measured and which exceptions were closed. Zisheng Electric can align equipment documentation and substation interface records with the agreed project acceptance plan.
Review substation bolted connection records: verify torque instructions, tool traceability, witness marks and reassembly evidence before EPC handover.
View detailsPlan substation special tools handover: verify equipment compatibility, torque adapters, tool records, storage and owner acceptance before EPC demobilization.
View detailsReview transformer temperature-rise FAT evidence with a practical EPC checklist. Align the test duty, cooling mode, measurement channels, calculations, uncertainty and deviation closure before acceptance.
View detailsReview a dry-type transformer fan upgrade before ordering: confirm the approved rating, electrical capacity, room ventilation, failure response and handover evidence.
View details